The aim of the project is to develop an environmentally and economically sound solar farm.

ICN, Neoen Australia and Downer Group invite you to the Numurkah Solar Farm briefing session. The briefing will include a project overview, outline of the construction program, procurement process and networking opportunities.

The Numurkah Solar Farm is a 100 MW renewable energy project consisting of approximately 350,000 solar panels installed on 500 hectares of land 6km south of Numurkah in Victoria.

  • When: Monday 4 December
  • Time: 4.00pm - 5.30pm
  • Where: Numurkah Visitors Centre, Presidents Room, 99 Melville St
  • RSVP: Friday 1 December
  • Register: HERE

Who should attend? This briefing is specifically aimed at companies who have capability to support the following work packages:

 Materials:

Quarry materials supply (rubble class 3), quarry materials supply (bedding sand), concrete, diesel fuel, steel reo, water tank, building furniture, demountable building, cable ladder, conduit and accessories, cabling accessories, cables, earthing materials, hardware and consumables, substation steel structure.

 Labour:

Civil labour, electrical, testing crew, forklift operator, supervisor labour, management staff, accomodation, meals.

 Plant hire:

Crane Hire 20T, crane hire 130T, crane truck, cable laying equipment, crane hire 130T, excavator 20T, grader, forklift, ute, generator, site sheds, cleaning and waste disposal, water cart, tipper and backhoe.

 Subcontractors:

Clearing, drilling, under-boring, tracker assembly, PV panel install, pile install, survey

pile testing, transport local, security service, site Hv auditing, geotech etc, fencing, vegetation screening, cable term, substation civil works, substation electrical install, cleaning/janitorial.

Contact: Noel Morton